Kavsakbendi

Kavsak Bendi HEPP, Turkey

POST-TENSIONING SYSTEMS

 

Project:
Kavsak Bendi HEPP hydroelectric power plant, Turkey

 

Client:
Enerji SA

 

Construction period:
2012 - 2014

 

Construction company:
AGE Insaat ve Ticaret

 

Supplier:
ANP - Systems GmbH

 

Scope of supply:
SAS 950/1050 pre-stressing thread bars, diameter 36 mm. 284 bar tendons with bond.

 

Application:    
ANP - Systems supplied, installed, stressed and grouted  tendons. The tie back anchors transfer load congestion from the pivot points of the water weir into higher areas of the concrete structure. Tension load is 840 KN.